Home

PMP Earned Value: Variances and Indexes

|
Updated:  
2016-03-26 14:21:16
|
From The Book:  
No items found.
PMP Exam Prep For Dummies
Explore Book
Buy On Amazon

On the PMP certification exam, you'll see five to ten questions on variances and indexes. Here's fundamental information that project managers need to determine cost and schedule variances and indexes.

  • For variance and indexes, always start with EV.

  • When looking for information on schedule, use PV.

  • When looking for information on cost, use AC.

  • For a variance, subtract.

    • SV = EV – PV

    • CV = EV – AC

    • Negative is bad; positive is good.

  • For an index, divide.

    • SPI = EV / PV

    • CPI = EV / AC

    • Less than 1.0 is bad, greater than 1.0 is good.

About This Article

This article is from the book: 

No items found.

About the book author: