- Base: The template on which all other calendars are built. Three base calendars are available: Standard, Night Shift, and 24 Hours.
- Project: The default calendar for scheduling. You choose which base calendar template your particular project should use.
- Resource: Combines the base calendar settings with any exceptions (nonworking times, such as vacation time) that you set for a particular resource.
- Task: Provides a spot where you can set exceptions for a particular task.
Likewise, suppose that you assign a resource to work two weeks on a task in a company that uses a standard five-day workweek. If that resource's own calendar is set for a standard four-day workweek, the two weeks of work by that resource defer to the timing of the resource calendar for a total of only eight workdays.
The nature of a task can affect resource time. A two-week, effort-driven task isn't complete until its resources have invested two weeks (according to the project calendar or task calendar) of effort.